Budget Performance Analysis

On Track
CategoryTypeBudgetedActualVariance% VarianceStatus
Site Preparation
CAPEX$450,000$425,000$25,000-5.6%
Seedlings & Planting
CAPEX$500,000$487,000$13,000-2.6%
Infrastructure
CAPEX$280,000$295,000+$15,000+5.4%
Monitoring & Compliance
OPEX$120,000$108,000$12,000-10.0%
Management & Admin
OPEX$200,000$180,000$20,000-10.0%

Capital Expenditure Details

DescriptionCategorySupplierStatusBudgetedActualVarianceDate
Initial site preparation - weed control and clearing
Invoice: GL-2022-0456
SITE PREPGreenLand Contractors
PAID
$180,000$165,000$15,0006/15/2022
Native seedlings - 50,000 units mixed species
Invoice: MVN-2022-1234
SEEDLINGSMurray Valley Nursery
PAID
$250,000$245,000$5,0008/20/2022
Mechanical planting services
Invoice: PPS-2022-0789
PLANTINGPrecision Planting Services
PAID
$320,000$335,000+$15,0009/10/2022
Livestock exclusion fencing - 15km
Invoice: RFC-2022-0234
FENCINGRural Fencing Co
PAID
$180,000$190,000+$10,0007/30/2022
Access roads and firebreaks
INFRASTRUCTURE
PLANNED
$120,000

Monthly Cash Flow Analysis

MonthBudgetedActualVariance% VariancePerformance
Jan 24$200,000$185,000$15,000-7.5%
Feb 24$250,000$267,000+$17,000+6.8%
Mar 24$180,000$172,000$8,000-4.4%
Apr 24$300,000$295,000$5,000-1.7%
May 24$220,000$238,000+$18,000+8.2%
Jun 24$180,000$165,000$15,000-8.3%

Financial Models & Analysis

DocumentTypeVersionCreated ByDateActions
Murray River Financial Model v3.2
Comprehensive financial model including sensitivity analysis
excel
v3.2LATEST
Sarah Chen7/15/2024
Carbon Price Sensitivity Analysis
Analysis of project returns under different carbon price scenarios
excel
v1.1LATEST
Michael Thompson7/10/2024